Project Duration
Stipulated Date of Commencement
October 31 2018
Stipulated Date of Completion /
Likely Date of Completion September 08 2019
Likely Date of Completion September 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,197,687.00
Awarded for
₹ 6,289,100.00
Project highlights
Relocation of Structures adjacent to the Main roads in Fatorda Constituency to ensure smooth flow of traffic
Contractors
M/s. Race Constructions
Consultants
M/s. Ankit Prabhudessai
Sub Works
This project involved 1 sub works. The details of the same available below
1
Widening of roads and relocation of structures in Fatorda Constituency – Phase II – Illumination of Footpath from Colva Circle to Ravindra Bhavan Circle at Fatorda, Margao, Goa
100% completed
Project Duration
Stipulated Date of Commencement
January 08 2018
Stipulated Date of Completion /
Likely Date of Completion January 22 2018
Likely Date of Completion January 22 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,181,939.00
Awarded for
₹ 3,492,794.00
Project highlights
Providing Streetlight Poles from Colva circle to Ravindra bhavan Circle.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Ankit Prabhudessai
See Similar Projects
Pedestrian Bridge Linking Central Library & Creek – Dynan Setu
View Project
Construction and upgradation of fishing jetty at Malim (North Goa) and Cortalim (South Goa).
View Project
Design & Construction of Bridge across river Zuari between Amona and Virdi.
View Project