Project Duration
Stipulated Date of Commencement October 21 2012
Actual Date of Completion December 27 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 144,727,214.00
Awarded for ₹ 142,275,590.00
Final Cost of Project ₹ 163,361,425.00

Project highlights

Jetty length of 184 meters constructed to provide facility for Barges, launches, Cruise Operators industry. Designed according to Holistic Design of Panaji like glass railing, Olivio Grande LED fitting . Equipped with underground sump tank, cathodic prevention system.

 
Contractors
M/s. Kargwal Constructions Pvt. Ltd., 103, First Floor, Runwal & Omkar Esquare, Opp. Sion-Chunnabhatti Signal, Off. Eastern Express Highway, Sion (E), Mumbai – 400 022.
Consultants
M/s. Madhav Kamat & Associates, Julieta Building, P. O. Box No.16, Swatantrya Path, Vasco-da-Gama, Goa.
 

See Similar Projects

Construction of Bus Stand at Marcel, Goa – Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.

View Project

Demolition Of Existing Bridge And Reconstruction Of Box Culvert On 18th June Road Over St. Inez Creek, Panaji-Illumination Work

View Project

Widening of road in Calangute – Baga.

View Project
x