Project Duration
Stipulated Date of Commencement
March 08 2004
Stipulated Date of Completion /
Likely Date of Completion September 07 2004
Likely Date of Completion September 07 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,951,068.00
Awarded for
₹ 17,629,111.00
Project highlights
The length of the bridge is 42 m with a total width of 12 m (two lane)
Contractors
M/s. Naik Constructions
Consultants
M/s. M. V. S. Borcar & Associates