Project Duration
Stipulated Date of Commencement
September 20 2007
Stipulated Date of Completion /
Likely Date of Completion June 19 2008
Likely Date of Completion June 19 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 30,958,791.00
Awarded for
₹ 36,323,192.00
Project highlights
The work consists of construction of bus stand, security room, electrical room and overhead tank. It involves civil work, internal electrification and roads.
Contractors
M/s. SMC Infrastructures Private Limited
Consultants
M/s. Rahul Deshpande & Associates