Project Duration
Stipulated Date of Commencement September 20 2007
Stipulated Date of Completion /
Likely Date of Completion
June 19 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 30,958,791.00
Awarded for ₹ 36,323,192.00

Project highlights

The work consists of construction of bus stand, security room, electrical room and overhead tank. It involves civil work, internal electrification and roads.

 
Gallery Image
Contractors
M/s. SMC Infrastructures Private Limited
Gallery Image
Consultants
M/s. Rahul Deshpande & Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Pedestrian Arch Bridge connecting Mandovi River Promenade and DB Road, over St. Inez Creek near ESG Building at Panaji

View Project
Similar Project

Dismantling of HT overhead lines, supplying & laying of HT underground cables at Panaji – Cable work from EDC substation to Chimbel junction.

View Project
Similar Project

Design and Construction of bridge at Patto in Panaji including approach roads

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.