Project Duration
Stipulated Date of Commencement September 21 2018
Actual Date of Completion June 15 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,292,386.00
Awarded for ₹ 9,083,500.00
Final Cost of Project ₹ 20,027,888.00

Project highlights

The scope of work includes:
1) Supply, installation, testing & commissioning of 33 KV, 3CX400 sq. mm, underground armoured cable – 4078 meters.
2) Supply, installation, testing & commissioning of 11 KV, 3CX300 sq. mm, underground armoured cable – 108 meters.
3) Dismantling of HT/LT overhead lines and Installation of new 100kVA distribution transformer centre.

 
Contractors
M/s. Consistent Engineers
Consultants
M/s. Nitin Arolkar
 

See Similar Projects

Construction of Sanskruti Bhavan in Salcete Taluka at Mandopa – Navelim and Davorlim.

View Project

supply and erection of new 11KV line with AB conductor from 33/11KV colony substation to M/s Rajiv Gandhi Kala Mandir

View Project

External painting of buildings for IFFI 2014.

View Project
x