Project Duration
Stipulated Date of Commencement January 22 2003
Stipulated Date of Completion /
Likely Date of Completion
July 21 2003
Status
100%
Completed
Cost (₹)
Estimated at ₹ 68,776,953.00
Awarded for ₹ 76,639,000.00

Project highlights

The bridge has four spans out of which two spans are over the river basin supported on three numbers of piers located in the river. Both abutments are on the river bank, one on Sanvordem and other on Curchorem side. The width of the carriageway is 7.5 m + 1.5 m wide footpath on both sides of the carriageway.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. TPF Engineering Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Improvement / Widening of road in Saligao – Calangute Constituency.

View Project
Similar Project

Improvement and Widening to four lane road from km.34/200 to km.35/600 at Navelim including construction of pavement at various places.

View Project
Similar Project

Construction of Bus Stand & Mini Depot at Sankhali, Goa – Erection of 11KV line from Electricity Department feeder to bus stand substation.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.