Project Duration
Stipulated Date of Commencement
January 22 2003
Stipulated Date of Completion /
Likely Date of Completion July 21 2003
Likely Date of Completion July 21 2003
Status
100%
Completed
Cost (₹)
Estimated at
₹ 68,776,953.00
Awarded for
₹ 76,639,000.00
Project highlights
The bridge has four spans out of which two spans are over the river basin supported on three numbers of piers located in the river. Both abutments are on the river bank, one on Sanvordem and other on Curchorem side. The width of the carriageway is 7.5 m + 1.5 m wide footpath on both sides of the carriageway.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. TPF Engineering Pvt. Ltd.
See Similar Projects
Improvement / Widening of road in Saligao – Calangute Constituency.
View Project
Improvement and Widening to four lane road from km.34/200 to km.35/600 at Navelim including construction of pavement at various places.
View Project
Construction of Bus Stand & Mini Depot at Sankhali, Goa – Erection of 11KV line from Electricity Department feeder to bus stand substation.
View Project