Project Duration
Stipulated Date of Commencement
June 24 2006
Stipulated Date of Completion /
Likely Date of Completion April 23 2007
Likely Date of Completion April 23 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 111,151,947.00
Awarded for
₹ 141,357,588.70
Project highlights
The length of the road is 26.5 km. The work involves hot mixing of the road, construction of site gutters, retaining walls including pipe culverts cross drainages, road signages & marking, crash barriers.
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Construction of Road Bridge at Balli in Quepem Constituency on Balli – Fatorpa MDR Road at Balli in Quepem.
View Project
Repairs and Resurfacing of PANAJI ROADS
View Project
Design and construction of bridge over river Satrem at Satrem, Sattari Taluka.
View Project





