Project Duration
Stipulated Date of Commencement
January 05 2004
Stipulated Date of Completion /
Likely Date of Completion July 04 2004
Likely Date of Completion July 04 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,750,000.00
Awarded for
₹ 12,880,000.00
Project highlights
• Length : 90 m.
• Carriage way 4.5 m wide with kerbs and railings on both the sides.
• Five spanned with two abutments and four piers all of which are resting on open foundation.
Contractors
M/s. Descon
Consultants
M/s. Kuvelkar Salkar Associates