Project Duration
Stipulated Date of Commencement April 07 2006
Actual Date of Completion May 10 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,419,884.00
Awarded for ₹ 54,735,320.00
Final Cost of Project ₹ 54,347,340.00

Project highlights

Hot mixing (laying of bituminous macadam and asphaltic concrete), lane marking, providing gutters and cross drainages wherever required. The approximate length of the road is around 14.6 kms.

 
Contractors
M/s. Madanant Construction Pvt. Ltd., M/s. Madanant Construction Pvt. Ltd.
Consultants
M/s. Keni & D’Souza, M/s. Keni & D’Souza
 