Project Duration
Stipulated Date of Commencement
February 22 2014
Actual Date of Completion
May 31 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,345,568.00
Awarded for
₹ 28,150,235.00
Final Cost of Project
₹ 19,489,404.00
Project highlights
Internal Roads of total approximate length of 5.7km hotmixed and widened at certain locations.
Contractors
M/s. Shaurya Construction Pvt. Ltd., M/s. Shaurya Construction Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Hot mixing & Improvement of Internal Roads in V. P. Navelim in Navelim Constituency.
100% completed
Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion July 04 2017
Likely Date of Completion July 04 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 42,752,453.00
Awarded for
₹ 44,016,624.00
Final Cost of Project
₹ 44,568,658.00
Project highlights
Internal Roads of total approximate length of 3.8km hotmixed and widened at certain locations. Widening of Tolleaband road done
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
See Similar Projects
Construction of Bus Stand & Market Complex at Pernem – Erecting 11 kV overhead line from feeder at the Electricity Department Substation to the Bus Stand Substation
View ProjectPainting, landscaping and other ancillary works along DB Road Panaji for IFFI 2017- SH: Resurfacing of Roads
View ProjectConstruction of Bridge at Mungul.
View Project