Project Duration
Stipulated Date of Commencement
February 27 2014
Actual Date of Completion
October 31 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 36,323,930.00
Awarded for
₹ 34,920,750.00
Project highlights
Construction of footpath from Sai Service Junction to Training College Junction at Porvorim.
Contractors
Consultants
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of footpath from Sai Service junction to training college junction at Porvorim – Electrical works
100% completed
Project Duration
Stipulated Date of Commencement
February 27 2014
Stipulated Date of Completion /
Likely Date of Completion July 15 2016
Likely Date of Completion July 15 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,232,612.00
Awarded for
₹ 9,932,510.00
Project highlights
The scope of work involves supply and installation of decorative street light poles on the Service road.
Contractors
M/s. Goa Friends Engineering and Electricals Pvt. Ltd
Consultants
M/s. Nitin Arolkar
See Similar Projects
Supply & Installation of Furniture for Government Schools and Colleges in the State of Goa
View ProjectRemodelling of existing Sewage Treatment Plant for GMC, Bambolim, Goa (C-Tech).
View ProjectConstruction of Building for Science Faculty at Goa University, Taleigao, Tiswadi Goa – Civil, electrification & land development work.
View Project