Project Duration
Stipulated Date of Commencement March 05 2016
Stipulated Date of Completion /
Likely Date of Completion
November 05 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 970,616,860.00
Awarded for ₹ 977,929,928.09

Project highlights

Construction of new Jetty

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd
Gallery Image
Consultants
M/s. Kuvelkar Salkar Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Bus Stand & Market Complex at Pernem – Erecting 11 kV overhead line from feeder at the Electricity Department Substation to the Bus Stand Substation

View Project
Similar Project

Construction of Bridge across Rua de Ourem Creek, Panaji

View Project
Similar Project

Demolition Of Existing Bridge And Reconstruction Of Box Culvert On 18th June Road Over St. Inez Creek, Panaji

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.