Project Duration
Stipulated Date of Commencement
February 26 2004
Stipulated Date of Completion /
Likely Date of Completion August 25 2004
Likely Date of Completion August 25 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,611,394.00
Awarded for
₹ 14,350,277.00
Project highlights
• First four lane bridge in Goa.
• The bridge serves as an important link joining the southern part of Goa to the Margao city.
• Length : 18.6 m, width : 19 m including footpaths.
• Length of approaches : 100 m, width : 19 m with adequate lighting and proper drainage system.
Contractors
M/s. Laxmi Civil Engg. Services Pvt. Ltd.
Consultants
M/s. Keni & D’Souza
See Similar Projects
Construction of approaches to Cumbarjua bridge including road link upto Khandola college.
View Project
Construction and upgradation of fishing jetty at Malim (North Goa) and Cortalim (South Goa).
View Project
Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Porvorim
View Project