Project Duration
Stipulated Date of Commencement
December 26 2014
Stipulated Date of Completion /
Likely Date of Completion May 25 2015
Likely Date of Completion May 25 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,94,72,456.00
Awarded for
₹ 5,46,71,553.08
Project highlights
Repairs and resurfacing roads in and around Panaji, Saligao, Ribandar, Taleigao, and Bambolim.
Contractors
M/s. Race Constructions
Consultants
M/s. Nitin Arolkar