Project Duration
Stipulated Date of Commencement December 26 2014
Actual Date of Completion November 30 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,94,72,456.00
Awarded for ₹ 5,46,71,553.08

Project highlights

Repairs and resurfacing roads in and around Panaji, Saligao, Ribandar, Taleigao, and Bambolim.

 
Contractors
M/s. Race Constructions
Consultants
M/s. Nitin Arolkar
 