Project Duration
Stipulated Date of Commencement January 14 2016
Actual Date of Completion June 17 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,883,534.00
Awarded for ₹ 54,586,026.00
Final Cost of Project ₹ 48,284,941.00

Project highlights

1. The Bridge was used to facilitate the Defence Expo 2016.
2. Length of the bridge and no. of spans: Single span of 24.75 mt long
3. Loading: One lane of Class 70R wheeled/ tracked or 2 lanes of Class ‘A’ which is critical.
4. Type & Depth of Foundations: Pile Foundation – On Fatorpa Side 30.2 m & on Balli Side 26.19 m
5. Sub-Structure: RCC
6. Bearing: POT PTFE
7. Superstructure: Composite steel plate girder, RCC deck slab.
8. Carriageway and footpath widths: 7.5 mts. Carriageway & 1.5 m footpath on each side.
9. Details of wearing coat: 50 mm D.B.M. with 25mm Polymerized Modified Bitumen, 3mm waterproofing membrane
10. Details of Expansion Joints: Strip seal expansion joints.

 
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Vijaykumar Sawant Associates
 

See Similar Projects

Improvement and Upgradation of the road from Borim Bridge Junction to Kamaxi Temple and Shivnath Temple in Shiroda Constituency.

View Project

Construction of Concrete Road for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka

View Project

Uguem Bridge

View Project
x