Project Duration
Start Date 30/7/2008
End Date 15/3/2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 41,612,031.00
Awarded for ₹ 80,505,716.00
Final Cost of Project ₹ 70,840,902.00

Project highlights

Simply supported RCC bridge of length 66 meters and width 12.10m (including footpaths) constructed on the Khandepar river as connecting link to Codli and Dabal villages.

 
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd
Consultants
M/s. Mahimtura Consultants Pvt. Ltd., M/s. Mahimtura Consultants Pvt. Ltd.
 