Project Duration
Stipulated Date of Commencement
December 15 2006
Actual Date of Completion
May 19 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,739,000.00
Awarded for
₹ 26,300,000.00
Final Cost of Project
₹ 50,285,886.00
Project highlights
The bridge has an overall length of 150 mts. with a carriage way width of 5.5 mts. The overall length of the approaches is around 300 mts. This bridge serves as an important connectivity to the residents of Ambeshi to proceed to market area like Ponda via Ganjem during monsoon. These people had to walk around 3 kms. through hilly terrain and mining areas to reach market area like Pale thus causing inconvenience especially to school children, ladies etc.
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd
Consultants
M/s. Kuvelkar Salkar Associates J/v M/s. Decom Consultant, M/s. Kuvelkar Salkar Associates J/v M/s. Decom Consultant
See Similar Projects
Construction of Concrete Pavement Road and other development work from Miramar Circle to NIO Circle and Raj Bhavan
View ProjectCompletion of balance work of culvert opposite to home science college at Miramar.
View ProjectHot mixing & Improvement of Internal Roads in V. P. St. Jose de Areal in Velim Constituency.
View Project