Project Duration
Stipulated Date of Commencement May 11 2016
Stipulated Date of Completion /
Likely Date of Completion
April 07 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,917,386.00
Awarded for ₹ 11,661,561.16

Project highlights

Repairs/ upgradation of schools which include proviison of new double skin galvalum sheet roofing, tiling, painting etc.

 
Gallery Image
Contractors
M/s.K.G Thomas
Gallery Image
Consultants
M/s.Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Furnishing Work of Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
Similar Project

Repairs/ Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical – GHS Zambaulim

View Project
Similar Project

Reconstruction of school at GPS Bicholim (Central) – Additional Work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.