Project Duration
Stipulated Date of Commencement May 23 2013
Actual Date of Completion October 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,265,380.00
Awarded for ₹ 7,015,854.00
Final Cost of Project ₹ 7,595,150.00

Project highlights

School Building with 4 classrooms of international size 60 sq. m

 
Contractors
M/s. H. Candolcar & Sons
Consultants
M/s. Datta Kare Associates
 