Project Duration
Stipulated Date of Commencement
September 27 2019
Stipulated Date of Completion /
Likely Date of Completion June 06 2020
Likely Date of Completion June 06 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,615,867.00
Awarded for
₹ 6,273,962.92
Project highlights
Roofing work, Tilling work Painting , Repairing of window & doors,plumbing works, electrical works etc.
Contractors
M/s. R.G. Contractors & Engineers,
Consultants
M/s Bhaskar Wagle & Associates