Project Duration
Stipulated Date of Commencement
February 28 2014
Stipulated Date of Completion /
Likely Date of Completion February 27 2015
Likely Date of Completion February 27 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,000,000.00
Awarded for
₹ 20,000,000.00
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. M.B. Kinlekar
Consultants
M/s. Nitin Arolkar
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa – Pernem Taluka: Package – V (GPS Tiwade Dhargal, GPS Chandel, GPS Madkai Ozari, GPS Varkhand, GPS Bhatpavni, GPS Patradevi, GPS Fakirpata Torse, GPS Tulaskarwadi)
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Package N – Sattari Taluka – GPS Nanus, GPS Zarme,GPS Dabem, GPS Kumthol, GPS Karanzol, GPS Karmali Budruk) – Balance works.
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Ponda Taluka: GPS Volvoi & GPS Veling
View Project