Project Duration
Stipulated Date of Commencement
January 09 2019
Stipulated Date of Completion /
Likely Date of Completion September 19 2019
Likely Date of Completion September 19 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,498,302.00
Awarded for
₹ 8,804,928.00
Project highlights
Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari Taluka
Contractors
M/s. Mahabaleshwar M. Naik
Consultants
M/s. Bhaskar Wagle and Associates