Project Duration
Stipulated Date of Commencement
October 31 2019
Stipulated Date of Completion /
Likely Date of Completion July 18 2020
Likely Date of Completion July 18 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,761,735.00
Awarded for
₹ 9,578,476.26
Project highlights
Repairs/Renovation works