Project Duration
Stipulated Date of Commencement
December 18 2013
Stipulated Date of Completion /
Likely Date of Completion January 31 2014
Likely Date of Completion January 31 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,89,51,400.00
Awarded for
₹ 5,10,72,960.00
Project highlights
Branding of venues and main roads
Contractors
M/s. Purple Focus Pvt. Ltd.
Consultants
In-house (GSIDC) & LUGOC,