Project Duration
Stipulated Date of Commencement December 18 2013
Actual Date of Completion January 31 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,89,51,400.00
Awarded for ₹ 5,10,72,960.00
Final Cost of Project ₹ 30,645,377.00

Project highlights

Branding of venues and main roads

 
Contractors
M/s. Purple Focus Pvt. Ltd., M/s. Purple Focus Pvt. Ltd.
Consultants
Inhouse & LUGOC, Inhouse & LUGOC
 