Project Duration
Stipulated Date of Commencement
January 22 2019
Stipulated Date of Completion /
Likely Date of Completion September 21 2019
Likely Date of Completion September 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,168,069.47
Awarded for
₹ 13,420,526.14
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s. S. Kumar Homes,
Consultants
M/s. Datta Kare Associates