Project Duration
Stipulated Date of Commencement
January 18 2019
Stipulated Date of Completion /
Likely Date of Completion September 27 2019
Likely Date of Completion September 27 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,770,090.00
Awarded for
₹ 8,544,274.32
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates