Project Duration
Stipulated Date of Commencement
November 14 2017
Actual Date of Completion
October 29 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 5,000,000.00
Final Cost of Project
₹ 4,503,942.00
Project highlights
Repairs of Govt. Schools in Pernem Taluka – Civil, Plumbing, Electrical works – Rate contracts
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates