Project Duration
Stipulated Date of Commencement
January 03 2019
Stipulated Date of Completion /
Likely Date of Completion September 12 2019
Likely Date of Completion September 12 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,794,104.29
Awarded for
₹ 11,189,253.28
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Nitin Arolkar
See Similar Projects
Interior Furniture Works
View Project
Repairs /Upgradation & Maintenance of Government schools in the sate of Goa -Civil,Plumbing & Electrical works – Package IVA (Sanguem Taluka)
View Project
Repairs/ upgradation of School in the state of Goa Package -V (Quepem & Canacona Taluka)
View Project





