Project Duration
Stipulated Date of Commencement
July 30 2018
Stipulated Date of Completion /
Likely Date of Completion February 12 2019
Likely Date of Completion February 12 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,437,047.00
Awarded for
₹ 8,076,973.56
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. KG Thomas
Consultants
M/s. Manoj M. Amshekar