Project Duration
Stipulated Date of Commencement
February 12 2021
Stipulated Date of Completion /
Likely Date of Completion October 21 2021
Likely Date of Completion October 21 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,963,251.00
Awarded for
₹ 10,073,828.68
Contractors
M/s. Sun Infrastructures
Consultants
M/s. Vaishali Pednekar Associates