Project Duration
Stipulated Date of Commencement
June 29 2017
Actual Date of Completion
August 12 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,40,35,435.00
Awarded for
₹ 1,49,08,082.49
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. H Candolkar and Sons
Consultants
M/s. Creative Abode