Project Duration
Stipulated Date of Commencement
September 11 2018
Stipulated Date of Completion /
Likely Date of Completion July 25 2019
Likely Date of Completion July 25 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,554,175.00
Awarded for
₹ 8,534,225.25
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-
Contractors
M/s.Shrusti Construction
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs/upgradation & maintenance of Govt. schools in the State of Goa – Sattari Taluka: Package D- GPS Brahmkarmali, GPS Dhave, GPS Kankire, GHS Nagargao, GPS Charvane, GPS Varshe, GHS Dhabem
View Project
Construction of new building and repairs of existing building for Government Higher Secondary School at Canacona – Erection of Distribution Transformer Centre (DTC) of 200 KVA
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa: Package -I (GPS Yeda, GPS Kuskem, GPS Barse, GPS Mahalbadem in Canacona Taluka
View Project