Project Duration
Stipulated Date of Commencement December 27 2021
Actual Date of Completion July 30 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,316,898.50
Awarded for ₹ 2,285,430.00

Project highlights

Erection of Distribution Transformer Centre (DTC) of 200 KVA for new and existing building of Government Higher Secondary School at Canacona.

 
Contractors
M/s.Siddharud Electricals
Consultants
M/s. Manoj Amshekar
 