Project Duration
Stipulated Date of Commencement
July 26 2018
Stipulated Date of Completion /
Likely Date of Completion March 25 2019
Likely Date of Completion March 25 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 35,100,310.00
Awarded for
₹ 31,895,244.00
Project highlights
Interior works for Sanjay School building at Vasco & Porvorim which includes new modular furnitures for special childrens, carpentary works, new stage along with acoustics etc.
Contractors
M/s. Macro Enterprises
Consultants
M/s Rajesh Kenkre