Project Duration
Stipulated Date of Commencement
September 20 2018
Actual Date of Completion
December 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,400,666.00
Awarded for
₹ 9,172,221.87
Final Cost of Project
₹ 8977456
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
Shri Hari Krishna Constructions
Consultants
M/s. Manoj Amshekar