Project Duration
Stipulated Date of Commencement November 18 2016
Actual Date of Completion January 31 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,706,391.69
Awarded for ₹ 3,748,767.75

Project highlights

The Operation table supplied at new burns ward at GMC will help in perform surgical procedures.

 
Contractors
M/s. Medex India Pvt. Ltd,
Consultants
In house
 

See Similar Projects

Construction of two number of sheds for treatment of dry waste within the Corporation of the City of Panaji (CCP) jurisdiction.

View Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa