Project Duration
Stipulated Date of Commencement
August 20 2014
Stipulated Date of Completion /
Likely Date of Completion November 19 2014
Likely Date of Completion November 19 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 60,002,811.80
Awarded for
₹ 54,000,000.00
Project highlights
Temporary office premises for GSIDC office and the District & Sessions Court untill the permanent premises is ready to be occupied.
Contractors
M/s. Knchan Associates,
Consultants
M/s. Ameet Sukhthankar Architect,