Project Duration
Stipulated Date of Commencement
July 10 2015
Stipulated Date of Completion /
Likely Date of Completion October 09 2015
Likely Date of Completion October 09 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,355,777.00
Awarded for
₹ 4,144,116.80
Project highlights
Construction of Box Culvert Work.
Contractors
M/s.Aashirwad Constructions
Consultants
M/s.Mahimtura Consultants Pvt. Ltd.