Project Duration
Stipulated Date of Commencement
December 21 2007
Actual Date of Completion
April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 573,453,985.00
Awarded for
₹ 734,634,449.00
Final Cost of Project
₹ 977,494,975.00
Project highlights
Basement + Ground + 5 RCC framed structure
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.