Project Duration
Stipulated Date of Commencement
April 22 2012
Stipulated Date of Completion /
Likely Date of Completion May 07 2012
Likely Date of Completion May 07 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 87,89,272.80
Awarded for
₹ 8,250,144.00
Project highlights
Decorative Glazing works

Contractors
M/s. R. S. Lawande

Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.