Project Duration
Stipulated Date of Commencement
January 02 2017
Actual Date of Completion
June 30 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 42,824,134.00
Awarded for
₹ 38,640,483.88
Final Cost of Project
₹ 36,658,597.00
Project highlights
Upgraded offie premises for GSIDC in EDC House
Contractors
M/s. Mahendra Relators & Infrastructure Pvt.Ltd
Consultants
M/s. Intrinsic Classics,
See Similar Projects
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa-Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa.