Project Duration
Stipulated Date of Commencement
January 02 2017
Stipulated Date of Completion /
Likely Date of Completion July 01 2017
Likely Date of Completion July 01 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 42,824,134.00
Awarded for
₹ 38,640,483.88
Project highlights
Upgraded offie premises for GSIDC in EDC House

Contractors
M/s. Mahendra Relators & Infrastructure Pvt.Ltd

Consultants
M/s. Intrinsic Classics,