Project Duration
Stipulated Date of Commencement January 02 2017
Stipulated Date of Completion /
Likely Date of Completion
July 01 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 42,824,134.00
Awarded for ₹ 38,640,483.88

Project highlights

Upgraded offie premises for GSIDC in EDC House