Project Duration
Stipulated Date of Commencement
August 11 2012
Actual Date of Completion
March 15 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,09,68,986.00
Awarded for
₹ 6,849,960.00
Contractors
Shanti Electrical Enterprises Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.