Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion June 09 2019
Likely Date of Completion June 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,557,570.00
Awarded for
₹ 3,871,916.24
Project highlights
Repairs/Upgradation and Maintenance work – Civil, Plumbing and Electrical works, sanitary work, land development, compound wall, etc.
Contractors
M/s. R.G. Contractors & Engineers
Consultants
M/s Nitin Arolkar
See Similar Projects
Repairs, Upgradation & Maintenance of Government schools in the state of Goa – Bicholim Taluka – Package M (GHS Amona, GPS Ambegal Pale).
View Project
Construction of Anganwadi Centres from NABARD Assistance – Package II (GPS Sangao Ozari, GPS Sakral Torse).
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil,Plumbing & Electrical works – Package B (Mormugao Taluka) GPMS Curpawada, GPMS Jetty.
View Project





