Project Duration
Stipulated Date of Commencement November 16 2014
Actual Date of Completion December 03 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,621,286.20
Awarded for ₹ 53,568,912.61
Final Cost of Project ₹ 71,420,609.00

Project highlights

Total Proposed Area for Renovation + Construction – 1780 Sqm
Ground Floor
? Vocational training halls – 6 Nos.
? Separate changing rooms & toilets
? Ramps & lifts for differently abled students
? Children friendly colour schemes
? Landscaped central open to sky courtyard
? Well designed podium/stage for extracurricular functions
First Floor
? 10 Classrooms for differently abled Students
? A common / multipurpose hall for students
? Corridor painted in children friendly colour schemes
? Floor pattern with surface texture for differently abled students
Second Floor
? Auditorium of capacity 500 Nos. with green rooms & toilets
? 8 Classrooms for differently abled students
? Conference room for administration and teachers
? Floor pattern with surface texture for differently abled students
The building is provided with CCTV Surveillance System, Fire fighting system, Public Address system, Air conditioning for Multipurpose hall and 2 new additional lifts.

 
Contractors
M/s H Candolkar & Sons
Consultants
M/s Archivista
 

Sub Works

This project involved 3 sub works. The details of the same available below

1

Infrastructure Works for Sanjay Centre for Special Education At Porvorim – HVAC work

100% completed
 
Project Duration
Stipulated Date of Commencement June 13 2016
Stipulated Date of Completion /
Likely Date of Completion
May 05 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,405,439.00
Awarded for ₹ 2,390,319.50
Final Cost of Project ₹ 2,412,284.00

Project highlights

Air conditioning work

 
Contractors
M/s. Shree Manguirish Airconditioning Co
Consultants
M/s. Archivista Engineering Projects. Pvt. Ltd.
2

Infrastructure Works for Sanjay Centre for Special Education at Porvorim- Supply, Installation, Testing and Commissioning of 11kV HT Sub Station

100% completed
 
Project Duration
Stipulated Date of Commencement July 26 2016
Stipulated Date of Completion /
Likely Date of Completion
March 01 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 999,534.00
Awarded for ₹ 1,044,450.00
Final Cost of Project ₹ 1,393,619.00

Project highlights

The scope of work includes supply, installation, testing & commissioning of :
a) 160kVA,11/.415kV Distribution transformer
b) 11kV Load Break Switch
c) HT Metering cubicle and other allied electrical works.

 
Contractors
M/s. Aditya Electromech Services
Consultants
M/s. Archivista Engineering Projects. Pvt. Ltd.
3

Infrastructure Works For Sanjay Centre For Special Education at Porvorim-SH:Fire safety and exit signages work

100% completed
 
Project Duration
Stipulated Date of Commencement October 05 2020
Stipulated Date of Completion /
Likely Date of Completion
November 01 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 236,180.00
Awarded for ₹ 189,250.00
 
Contractors
M/s. R K Infra
Consultants
Inhouse (GSIDC)

See Similar Projects

Construction of Government Primary School at Shantinagar – Pissurlem in Sattari Taluka.

View Project

Furniture work.

View Project

Construction of Girls Hostel at Goa Medical College and Hospital, Bambolim, Goa.

View Project
x