Project Duration
Stipulated Date of Commencement
February 22 2019
Actual Date of Completion
October 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,543,158.00
Awarded for
₹ 10,992,111.60
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s Sushant Khedekar
Consultants
M/s Bhaskar Wagle Associates