Project Duration
Stipulated Date of Commencement
May 08 2006
Stipulated Date of Completion /
Likely Date of Completion August 07 2006
Likely Date of Completion August 07 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,447,398.00
Awarded for
₹ 51,402,737.00
Project highlights
Hot mixing (laying of bituminous macadam and asphaltic concrete), lane marking, laying pavers wherever required. The approximate length of the road is around 11.8 kms.
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Conversion of Overhead Lines to underground system and installation of 11KV & LT equipment’s along the road from NIO circle to Dona Paula Jetty and NIO circle to Rajbhavan road
View Project
Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) -Electrical work
View Project
Improvement and Upgradation of the road from Borim Bridge Junction to Kamaxi Temple and Shivnath Temple in Shiroda Constituency.
View Project