Project Duration
Stipulated Date of Commencement
January 06 2021
Stipulated Date of Completion /
Likely Date of Completion January 15 2022
Likely Date of Completion January 15 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 34,651,789.37
Awarded for
₹ 32,988,178.00
Project highlights
1015 m long Pedestrain Pathway including 5 Culverts from Power House junction to Railway Station.

Contractors
M/s. Naik Constructions

Consultants
M/s. Shrikhande Consultant Pvt. Ltd.