Project Duration
Stipulated Date of Commencement January 08 2022
Actual Date of Completion June 03 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 121,210,152.00
Awarded for ₹ 119,829,470.55

Project highlights

Bridge consists of span arrangement 42.5m x 2 Nos.= 85 mts Foundation-Pile foundation of 1.2m dia & length 25m are proposed. Pile foundation will be in M35 concrete with 8mm liners. Pile caps will be supported on piles. Sub structure comprises of RCC plate piers, RCC pier cap with pier pedestals. Grade of concrete shall be M35. Superstructure comprises of composite steel concrete construction. RCC deck slab is supported on steel work spanning between piers. Steel work comprises of plate girders for 42.5m span. Length of Approache roads : 156m (Melauli Side) & 105m (Paikul Side).

 
Contractors
M/s. Surabhi Counstructions
Consultants
M/s. Vijay Kumar Sawant Associates
 

See Similar Projects

Improvement and Upgradation of the road from Borim Bridge Junction to Kamaxi Temple and Shivnath Temple in Shiroda Constituency.

View Project

Improvement and Upgradation of the existing MDR from Dandevaddo to Chandor via Sarzora and Guddi in Cuncolim Constituency.

View Project

Construction of Bus Stand at Marcel, Goa – Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.

View Project
x