Project Duration
Stipulated Date of Commencement February 26 2014
Actual Date of Completion December 21 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,20,38,902.00
Awarded for ₹ 88,735,464.00
Final Cost of Project ₹ 82,437,808.00

Project highlights

Jetty length of 104 meters constructed to provide facility for Barges, launches, Cruise Operators industry. Designed according to Holistic Design of Panaji like glass railing, Olivio Grande LED fitting . Euipped with cathodic prevention system.

 
Contractors
M/s. Kargwal Constructions Pvt. Ltd., 103, First Floor, Runwal & Omkar Esquare, Opp. Sion-Chunnabhatti Signal, Off. Eastern Express Highway, Sion (E), Mumbai – 400 022.
Consultants
M/s. Madhav Kamat & Associates, Julieta Building, P. O. Box No.16, Swatantrya Path, Vasco-da-Gama, Goa.
 

See Similar Projects

Upgradation of the Road connecting Integrated School Complex to NH17 – Civil, Plumbing & Electrical works

View Project

Demolition Of Existing Bridge And Reconstruction Of Box Culvert On 18th June Road Over St. Inez Creek, Panaji-Illumination Work

View Project

Construction of Bus Stand at Mapusa, Goa – Land Development work (Phase I).

View Project
x