Project Duration
Stipulated Date of Commencement October 23 2012
Stipulated Date of Completion /
Likely Date of Completion
November 02 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,383,028.75
Awarded for ₹ 22,999,093.20

Project highlights

The RCC Simply supported Bridge is (Approx.) 35m in length comprising of 02 spans (approx. 17mts) supported by a central pier and on two abutment walls on both banks of the rivulet. •
The total length of approach roads is approx 400mts.

 
Gallery Image
Contractors
M/s. Indiana Build Infrastructure Pvt. Ltd.
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates (PMC)
 
Similar Projects

See Similar Projects

Similar Project

Improvement and Upgradation of road network from MDLB Hospital to Baina Sea Shore, Shafi Masjid to Baina Recreational Club, Bharat lines to Headland Sada Junction in Mormugao Constituency.

View Project
Similar Project

Hot mixing & Improvement of Internal Roads in V. P. Navelim in Navelim Constituency.

View Project
Similar Project

Design and Construction of Bridge across River Mandovi at Panaji including approaches on NH 17 between Pundalik Nagar Junction (Porvorim) and Merces Junction

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.